August 12, 2014 (Job 708)
On August 12, 2014 the East Bay Municipal Utility District awarded the Summit Reservoir and Shasta / Woods Pumping Plant (Specification #2070) to Steve P. Rados, Inc. The contract value for this project is $15,995,280, and is anticipated to take
July 9, 2014 (Job 707)
On July 9, 2014 the City of Sacramento awarded the 7th Street Sewer Replacement (P to K Streets) project to Steve P. Rados, Inc. The project, valued at $4,576,410 is scheduled to start in September 2014 and should be completed
July 1, 2014 (Job 706)
On July 1, 2014 Caltrans awarded the Horsethief Creek Bridge project (#08-0J8504) to Steve P. Rados, Inc. The project involves the reconstruction of the Horsethief Creek bridge near Silverwood Lake, on Highway 138 east to Interstate 15 near Hisperia, CA.