Expo 2 Reaches Halfway Point, Achieves 1 Million Safe Hours
"Skanska-Rados Joint Venture (SRJV) reached the half way point in construction of the Exposition Transit Corridor, a 6.6-mile extension from Culver City, Calif., to Santa Monica. SRJV has worked one million hours worked on the project without a lost time
SACRAMENTO WATER TREATMENT PLANT
During the $113.7 million rehabilitation of the City of Sacramento Water Treatment Plant located on Water Street in Sacramento, Rados is to install various 66” and 84” diameter pipes, risers, and manifolds. Rados’ work will be staged throughout the duration
BDPL5 Cordilleras Micro-Tunnel
The installation of 60” welded steel pipe; 465 LF by tunneling and 920 LF by open cut method. The project also included the installation of special fittings, corrosion protection, air vacuum assemblies, roadway restoration of Bennett Road in Redwood City,
June 26, 2013 (Job 703)
On June 26, 2013 the Sanitation District of the County of Los Angeles, District 2, awarded to Steve P. Rados, Inc. a $36,963,829 contract (Contract # 4779) for the upgrade of the Long Beach Main Pumping Plant. Major items of work
May 23, 2013 (Job 701)
On May 23, 2013, Rados was awarded a $5,646,695 subcontract from C. Overaa & Co. of Richmond, CA, to install certain 66” and 84” diameter pipes, risers, and manifolds in conjunction with a $113.7 million contract Overaa has with the
April 4, 2013 (Job 702)
On April 4, 2013 the Exposition Metro Line Construction Authority awarded Contract XP-8903-001 to Skanska-Rados, Joint Venture, for the construction of a bikeway and appurtenances along our current EXPO 2 project. Although this bikeway will be located adjacent to the EXPO
October 8, 2012 (Job 295)
On October 8, 2012, Steve P. Rados, Inc was awarded a subcontract from the R. J. Noble Company of Orange, CA to build a bridge as a part of Noble’s contract with the City of Tustin, for the Tustin Ranch Road Extension
June 9 2012 (Job 297)
On June 9, 2012 the San Francisco Public Utilities Commission awarded the Seismic Upgrade of Division Pipelines No. 3 and No. 4 at the Hayward Fault contract to Steve P. Rados, Inc. Referred to as SFPUC Contract No. WD-2629, this $31,370,000
March 28, 2012 (Job 296)
On March 28, 2012 the Olivenhain Municipal Water District (located north of San Diego, near San Marcos) awarded a $2,739,000 contract to Steve P. Rados, Inc. The work on this contract will be located a two sites. At the first site on