Contract No.: 7604
Contract Amount: $18,232,560
Job Duration: September 2015 through December 2017
Agency: Los Angeles Department of Water and Power
Work Performed: Steve P. Rados has partnered with the Los Angeles Department of Water and Power to reconstruct the Elysian Reservoir. The project entails the installation of 950LF of 36” and 40” WSP. This will be the new bypass line. Three underground vaults, two exterior buildings, electrical and mechanical will upgrade the reservoir including the installation of the floating cover. The reservoir will be re-paved, new fence will be installed and landscaping on the damn face that faces the 110 Freeway will complete the upgrade of the Elysian Reservoir.