On January 5, 2023, Steve P. Rados, Inc. submitted its bid to the Central California Irrigation District (CCID) in the amount of $9,932,680 to construct over 1,900-lf of 36” and over 5,045-lf of 48” water pipelines; a new 35 cfs cast-in-place pump station; and the construction of groundwater recharge basins. We are expecting the contract award soon and start construction in the beginning of April 2023 with completion by the end of 2023. We are looking forward to constructing our first project for the CCID and are encouraged with other opportunities in this area.